Completed front-end engineering; developed a ±10% Total Installed Cost estimate, and performed multi-discipline detailed design and project management for demolition, site preparation, and the Outside Battery Limits (OSBL) facilities required to support a new Hydrogen Unit at a Refinery in McPherson, Kansas.

Scope consisted of:

  • Demolition of tanks and piping
  • Site preparation, grading, drainage, roadways
  • New foundations, structures, and piperacks
  • Approx. 28,000 lf of new piping, and90 piping tie-ins
  • Utilities: steam, BFW, instrument air, plant air, Nitrogen, condensate, natural gas, and firewater
  • Electrical (new 35kV switchgear, electric power, UPS, emergency power)
  • Instrumentation